A fabricator building chemical piping in 2205 duplex needed filler wire with a ferrite balance that would survive both the WPS qualification and the chloride service behind it.
Duplex 2205 pipe joints, wall thickness 6 mm, GTAW root and hot pass with FCAW fill on some spools. The procedure demanded ferrite content in the qualified range, impact toughness at minus 20 °C, and pitting resistance consistent with the parent metal.
For duplex, the weld metal chemistry is the property. We supplied ER2209 with certified nickel on the high side of the range and nitrogen accounted for in the heat analysis, so the austenite reformation in the weld stayed in balance even with the dilution from the root pass.
Procedure qualification passed on the first coupon set: tensile through the weld, impact values above the specified minimum at minus 20 °C, and ferrite in range. The project consumed the balance of the heat in production welding without deviation requests.
Application example, anonymised from our order book. We supply the chemistry and the process window review; formal WPS qualification stays with your welding engineer.
A Turkish heat-treatment shop replaced nichrome elements that failed every 9 months with 0Cr25Al5 drawn to a m…
ViewBatteryA cell assembler in Eastern Europe was seeing intermittent weld failures traced to strip thickness variation. …
ViewSend the application data — atmosphere, temperature, cycle and current specification. We will tell you what we would change and quote both options.